Environmental work, Dams, Reservoirs and Rivers
- Excavation of foundations,
trenches footpaths, etc
- Dam Inspection
& remedial work
- Fish Habitat Improvement
work
- Shore Protection
- Weirs and River
Work
Shore
Protection work is undertaken wherever ground is being eroded from boat
wash, flooding, waves etc. and consists of rip rap type pitched stones
laid to protect river banks, lake shores etc. A geotextile layer is generally
placed behind the stones to prevent the fines being washed out.
LMC have undertaken investigations into a masonry wall dam with an earth
filled embankment which is leaking and carried out remedial work to try
and seal the leak. We have also carried out work building a channel suitable
for fish and other habitat improvements.
 |
|
 |
| Construction of masonry
wall at bottom of spillway |
|
Construction
of fishpass as a bypass to the spillway |
|
This section
of work includes the following:-
- Excavation
of foundations, trenches footpaths, etc
- Dam Inspection
& remedial work
- Fish Habitat
Improvement work
- Shore Protection
- Weirs and
River Work
Shore Protection
work is undertaken wherever ground is being eroded from boat wash,
flooding, waves etc. and consists of rip rap type pitched stones
laid to protect river banks, lake shores etc. A geotextile layer
is generally placed behind the stones to prevent the fines being
washed out.
LMC have also carried out work building a channel suitable for fish
and other habitat improvements.
 |
 |
 |
 |
| New galvanised steel sluice gate and walkway
installed on take off stream at Langdale |
Repaired sluice
gate at historic watermill in Heversham using greenheart 6*6”
timber for longevity |
5t excavator working on Foulshaw moss on drainage project on behalf of Cumbria Wildlife |
Plastic pile dam inserted in field ditch to control flooding as part of Natural England/DEFRA scheme |
Job
Profile – Yew Tree tarn
LMC
were contracted by National Trust to investigate the leakage
of Yew Tree Tarn Dam. A v-notch had been installed to measure
the extent of the leak but was found inadequate to measure
the volume actually leaking. LMC carried out a Site investigation,
installed a Flow Measuring device and carried out a diving
survey. The dam was found to contain no clay core but was
relying on the masonry wall. The mortar of which was in a
poor condition particularly around the base of the wall and
around the penstock, and was leaking at about 100m3/hr. LMC
then proposed a remedial repair and once NT had funding carried
out the work in Summer ‘04.
The work consisted of the following :-
- installation
of temporary inflatable bladder
- Install
grout bags along base of dam
- Install
concrete seal to base of dam
- Install
new penstock
- Seal
up spillway
- Re-furbish
fish pass
- Re-instate
small dam wall & V-notch
The leak
although not entirely sealed was reduced to about 10% of the
original volume.
|
|
|