Docks harbours and ports

LMC have undertaken work in docks and harbours including piling, mooring and fender work. The piling work included driving 10.5m long H section piles and casting 50t mooring bollards. LMC have replaced greenheart timber fenders in ports.

port work   welding pile caps
5 no. 60t dolphin structures constructed on the Tees   Welding Pile caps on site

timber fenders 50t bollard
Plastic pile protection with timber fenders installed at Rumneymead Harbour, Ullswater.
Pouring concrete in concrete base prior to fixing the 50t bollard. The form work had to be supported on a 45 degree slope.
We have installed 5 Mooring dolphins of 50t capacity on the River Tees near Seal Sands for large ships to berth at a chemical offloading facility. These involved removal of existing bollards, piling 25no. 1.5t H section steel sections, erection of form work to support 50t of concrete on a slope of 45 degrees and fixing the bollards in place.

We have also installed davits for disabled access and fenders on various jetties.